1.25 miles
The City of The Colony
Halff designed the reconstruction of 1.25 miles of North Colony Boulevard from a four-lane undivided thoroughfare to a four-lane divided thoroughfare with dedicated turn lanes at collector streets. The design included roadway and bike trail paving, drainage, water and sanitary sewer replacements, signals, fiber optics, retaining walls/headwalls, and landscape and irrigation. One critical design issue involved intersections with side streets and slip road entrances. A separate bike lane spans both sides of the road. Halff took special care when designing construction sequencing and traffic control plans to avoid disrupting activities at a nearby middle school.
							Halff Services 
 Involved
						
					- Environmental
 - Landscape Architecture
 - Local Infrastructure
 - Planning
 
- Structural Engineering
 - Surveying
 - Transportation
 
Let’s Connect